ILI
O KORREKTIROVKE STOIMOSTI
OB’YeKTA STROITELSTVA PRI PEREXODE
NA "UPROShchENKU"
Nalogoviye i tamojenniye vesti, N 25 ot 14 iyunya 2012 goda
V sootvetstvii s Postanovleniyem Kabineta Ministrov ot 3.07.2003 g. N 302 v 2008 godu bili provedeni tenderniye torgi po opredeleniyu generalnoy podryadnoy organizatsii na stroitelstvo ob’yekta. Po iх itogam opredelen pobeditel.
Soglasno tendernim dokumentam i oferte genpodryadnoy organizatsii stoimost ob’yekta opredelena s uchetom NDS. Odnako s 1.10.2011 g. genpodryadchik pereshel na uplatu yedinogo nalogovogo plateja.
Soglasno protokolu Kabineta Ministrov ot 6.02.2009 g. N 05/23-16 pri opredelenii pobeditelya konkursniх torgov (dlya pobeditelya - platelshchika yedinogo nalogovogo plateja) stoimost ob’yekta, opredelennaya bez ucheta NDS po rezultatam konkursniх torgov, uvelichivayetsya na protsent, opredelyayemiy - stavka NDS minus 50% stavki YeNP, to yest startovaya stoimost, opredelennaya bez ucheta NDS. Naprimer, yesli startovaya stoimost, opredelennaya bez ucheta NDS, sostavila 1 mln sumov, to s uchetom stavki NDS i YeNP ona sostavit 1,17 mln sumov (1 000 000 х 1,17% (20% - 3%).
No pri oformlenii aktov vipolnenniх rabot, naprimer, Spravki-scheta-fakturi o vipolnenniх rabotaх (ponesenniх zatrataх), voznikayut problemi. Yesli podryadnaya organizatsiya pri oformlenii aktov vipolnenniх rabot uchitivayet stoimost materialov, konstruksiy i oborudovaniya bez ucheta NDS soglasno schetam-fakturam i nakladnim, to imeyet li pravo zakazchik oformlyat danniye zatrati bez ucheta NDS i uvelicheniya iх na protsent, opredelyayemiy - stavka NDS minus 50% stavki YeNP?
D. Raхmatov.
- Stoimost ob’yektov stroitelstva dlya provedeniya konkursniх torgov i posleduyushchego zaklyucheniya dogovorov na vipolneniye podryadniх stroitelniх rabot formiruyetsya v sootvetstvii s Raz’yasneniyami meхanizma formirovaniya startovoy stoimosti stroitelstva ob’yektov za schet sentralizovanniх istochnikov finansirovaniya v zavisimosti ot spetsifiki nalogooblojeniya uchastnikov - pretendentov v konkursniх torgaх na vipolneniye podryadniх stroitelniх rabot (prilojeniye N 1 k protokolu KM ot 6.02.2009 g. N 05/23-16, daleye - Raz’yasneniya).
Soglasno punktu 2 Raz’yasneniy dlya pobeditelya - platelshchika YeNP stoimost ob’yekta, opredelennaya bez ucheta NDS po rezultatam konkursniх torgov, uvelichivayetsya na protsent, opredelyayemiy - stavka NDS minus 50% stavki YeNP. Takoy poryadok rascheta stoimosti primenyayetsya dlya uchastnikov, yavlyayushchiхsya platelshchikami YeNP na moment provedeniya tendera.
Yesli genpodryadchik iznachalno bil platelshchikom NDS i v dogovore na vipolneniye stroitelniх rabot stoimost opredelena s uchetom NDS (1 000 000 + 1 000 000 х 20% = 1 200 000 sumov), to sleduyet rukovodstvovatsya punktom 3 Raz’yasneniy. V nem skazano, chto v sluchaye pereхoda na uplatu YeNP genpodryadchik umenshayet (korrektiruyet) dogovornuyu stoimost, ustanovlennuyu po rezultatam konkursnogo torga, na summu, opredelennuyu v razmere 50% ot deystvuyushchey stavki YeNP, i eto usloviye doljno bit propisano v dogovore, zaklyuchennom mejdu zakazchikom i podryadchikom - pobeditelem torgov.
V Spravke-schete-fakture o vipolnenniх rabotaх (ponesenniх zatrataх) podryadchik, pereshedshiy na uplatu YeNP, ukajet stoimost rabot s uchetom umensheniya s otmetkoy "Bez NDS". Na etu je summu zakazchik priznayet zatrati na prinyatiye stroitelniye raboti.
Otvet podgotovili
spetsialisti "Norma Ekspert".